IMAGE - Info-Travaux
Info-works

Traffic lights

At the corner of Avenue Bédard and Chemin Saint-Louis

Work for the installation of traffic lights will begin week of September 21, 2020.

Civil work will be carried out:

  • September 24 to October 2, 2020 inclusively
  • Between 9 a.m. and 3 p.m.
  • With alternating traffic on one lane
  • Will be followed by electrical work tentatively from October 19 to October 26, 2020

Thank you for your patience, and for slowing down around the construction site to protect the lives of flagmen and women.

Rue Bois-Soleil : temporary closure


On Wednesday, September 9, Rue BOIS-SOLEIL will be closed in order to repair a culvert between Rues Pilon Street and Forest Hill.

Date of the work: Wednesday, September 9, 2020, starting at 7:00 a.m.

Detour: the detour takes place in both directions, via Rue Pilon, Rue du Vieux-Lac and Rue Forest Hill.

Thank you for your cooperation


Pine Ridge: temporary closure


On Tuesday, September 1st, Rue PINE RIDGE will be closed for aqueduct work, between Chemin Sainte-Angelique and Rue Toundra.


Detour: both directions, by Rues Maurice, Ravin, Toundra and Boréale.

Thank you for your collaboration


Montée Saint-Lazare: Partial Street Closure on Wednesday, August 19, 2020

Work begins at 7:00 a.m.

The City must proceed with emergency work.

The complete closure is taking place:

  • On Montée Saint-Lazare, between Place Turcotte and Rue des Loisirs
  • The detour is done using Bédard and Rue des Loisirs, both ways

A water shutdown (cut) may be necessary, followed by a preventive boil-water advisory.

City thanks residents for collaboration


Complete closure of exit 28 in Saint-Lazare

The work starts at 6:30 a.m. on Monday, August 17, 2020

The MTQ must rebuild a transverse culvert located at the beginning of this exit.

The complete closure is taking place:

  • This week (of August 17, 2020) until 6 p.m. on Friday, August 21, 2020.
  • The detour is done using exit 26.

In the event of adverse weather conditions or operational constraints, this work may be postponed or extended. In order to plan your travel properly, consult Québec 511 for information on current and upcoming obstacles. Follow Transports Québec on Twitter and on Facebook.

Construction of an underground electrical conduit

Work on Côte Saint-Charles at the corner of Chemin Saint-Louis

From Monday, August 10 to Friday, August 21, 2020

Bell undertakes construction work of an underground electrical conduit at the intersection of Côte Saint-Charles and Chemin Saint-Louis.

The work will be carried out:

  • From Monday, August 10 to Friday, August 21, 2020 (weather permitting)
  • Between 9 a.m. and 3 p.m.
  • With partial lanes

Trans-Northern Day closure


Location: TNPI network (affected land owners have been notified)
Date: starting in the week of April 27, 2020
Duration: approximately 4 weeks, depending on weather conditions
Reason: maintenance work

Additional Information: Targeted locations are identified following an in-line inspection of the pipe using a specialized tool. The work consists of clearing the pipe for inspection and, in the case of Once the work is completed, the land is restored to its original condition.

Last updated: 09/21/2020
Tous droits réservés, Ville de Saint-Lazare © 2002-2020
1960, chemin Sainte-Angélique, Saint-Lazare (Québec), J7T 3A3
Telephone: 450 424-8000

The Town ·  Municipal services ·  Things to do ·  History, maps & statistics ·  Environment ·  Transportation & public works ·  Public safety  ·   Contact us